1.
Please provide your organization's comments on the Interconnection Service Capacity and Deliverability Retention for Non-Operating Generating Facilities Straw Proposal and April 6 meeting discussion
I. Introduction and General Position
The Bay Area Municipal Transmission group (BAMx)[1] appreciates the opportunity to comment on the Interconnection Service Capacity and Deliverability Retention for Non-Operating Generating Facilities Straw Proposal, dated March 30, 2026, and April 6, 2026 meeting discussion. BAMx generally supports the direction of the Straw Proposal. The recommended actions appropriately address prolonged retention of unused interconnection service capacity and deliverability, which can otherwise be assumed in interconnection and transmission planning studies and contribute to unnecessary long-lead and costly reliability or deliverability network upgrades. This approach aligns with BAMx’s objective of supporting necessary and cost-effective transmission investments, while opposing unnecessary, excessive, or inefficient transmission upgrades that increase costs to ratepayers without commensurate reliability, policy or economic benefits.
II. Policy Alignment and Conceptual Support
BAMx agrees with CAISO’s core premise that extended non-operation of generating facilities—while retaining interconnection service capacity and deliverability—can distort planning assumptions by reserving capacity that may not reasonably be expected to return to service. (Straw Proposal §§1–2; Presentation Slide 6). Including such resources in base-case assumptions can affect study outcomes and increase the likelihood that network upgrades are identified to accommodate capacity that may ultimately remain unused.
BAMx therefore supports CAISO’s proposal to establish clearer expectations and timelines for generator owners to return facilities to service, pursue repowering, or enter the interconnection queue, with defined consequences where no action is taken. (Straw Proposal §3; Presentation Slide 7).
III. Requests for Clarification and Additional Information
A. Empirical Basis and Planning Impacts
To further inform stakeholder evaluation of the proposal, BAMx requests that CAISO provide data on the number of non-operating resources, including megawatt capacity, that have materially affected transmission or deliverability upgrade outcomes in recent interconnection studies or Transmission Planning Process (TPP) cycles. (Straw Proposal §1; Presentation Slide 6). Such information would help stakeholders appreciate the gravity of such identifiable planning inefficiencies in practice.
B. Distinguishing Speculative Retention from Legitimate Long-Term Outages
BAMx requests clarification on how CAISO intends to distinguish speculative retention of interconnection service capacity and deliverability from legitimate long-term outages due to factors outside a generator owner’s control including but not limited to, permitting challenges, equipment availability, financing constraints, labor constraints, and/or complex repowering efforts. (Straw Proposal §3; Presentation Slides 7–8).
In this context, BAMx also encourages CAISO to consider whether a requirement to submit a retirement or mothball affidavit after 12 consecutive months on outage is necessary in all circumstances. Certain forced outages—such as those resulting from major transmission equipment failures or other long-lead-time equipment replacements—may reasonably extend beyond one year despite diligent and commercially reasonable efforts by the generator owner to repair the facility and return it to service. Where a generator owner can demonstrate active repair efforts and a credible plan to return a resource to service within a reasonable timeframe (e.g., two to three years), BAMx requests that CAISO consider allowing such facilities to remain in outage status without requiring formal mothball designation. This flexibility would reduce unnecessary administrative burden while preserving CAISO’s visibility into resource status and would not undermine the proposal’s underlying objective of preventing speculative retention of interconnection service capacity and deliverability.
Clear articulation of the criteria or indicators CAISO will use in making this distinction, as well as the degree of discretion available to account for individual circumstances, will be important to ensure that bona fide repowering efforts are not inadvertently discouraged.
C. Treatment of Resources Already Offline
Finally, BAMx also requests clarification regarding how the proposed timelines would apply to generating facilities that were already offline for extended periods prior to the effective date of the tariff changes. (Straw Proposal §3; Presentation Slide 7). Specifically, BAMx seeks clarity on when the relevant compliance ‘clock’ would begin for such resources and whether transition provisions or initial compliance windows will be provided to avoid retroactive effects.
IV. Conclusion
BAMx supports CAISO’s efforts to better align retention of interconnection service capacity and deliverability with actual resource development and operational intent. The Straw Proposal represents a constructive step toward improving planning efficiency and protecting ratepayers from unnecessary transmission costs. (Straw Proposal §3; Presentation Slides 6–8). Subject to the clarifications requested above, BAMx looks forward to continued engagement as CAISO refines the proposal and develops final tariff language.
[1] BAMx consists of City of Palo Alto Utilities and City of Santa Clara, Silicon Valley Power.