Stakeholder input is essential to ISO planning processes. Similar to policy development, the ISO is committed to providing ample opportunities for stakeholder input into these processes.
Learn how to use the commenting tool:
*Date is tentative
Title | Status | Development | Decision | Implementation |
---|---|---|---|---|
2022-2023 Transmission planning process Jan 13, 2022 | Active | Jun 30, 2023 Final study plan posted | May 18, 2023 Board of Governors approval - transmission plan | |
20-Year transmission outlook (2021-2022) May 14, 2021 | Active | |||
20-Year transmission outlook (2023-2024) Aug 09, 2023 | Active | July 31, 2024 Final 20-year report posted | ||
2021-2022 Transmission planning process Feb 18, 2021 | Active | Mar 31, 2021 Final study plan posted | Mar 17, 2022 ISO Board of Governors approval - transmission plan | |
2023-2024 Transmission planning process Jan 16, 2023 | Active |
Jun 03, 2024 Board approved transmission plan posted Jul 18, 2024 Board of Governors for transmission plan extension |
May 23, 2024 Board of Governors approval | |
2024 Independent release Jul 22, 2024 | Active |
FERC Order 2222 BRS review
|
||
2024-2025 Transmission planning process Dec 28, 2023 | Active |
Oct 08, 2024 Comments due Oct 31, 2024* Final reliability study results posting Nov 12, 2024* Preliminary assessment of policy and economic studies posting Nov 13, 2024* Meeting Dec 02, 2024* Comments due Dec 09, 2024* Long-term LCR meeting Dec 23, 2024* Comments due Mar 31, 2025* Draft transmission plan posting Apr 15, 2025* Meeting May 2025* Board of Governors meeting May 30, 2025* Final board-approved transmission plan posting |
||
Annual policy initiatives roadmap process - 2021 Feb 28, 2020 | Completed | Jun 14, 2021 Final 2021 policy initiatives roadmap (updated) posted |
Jan 20, 2021 EIM Governing Body briefing Dec 17, 2020 Board of Governors briefing |
|
Annual policy initiatives roadmap process - 2022 May 11, 2021 | Completed |
Mar 16, 2022 Final 2022-2024 policy initiatives roadmap posted Dec 17, 2021 Revised draft 2022 policy initiatives catalog posted |
Feb 09, 2022 Board of Governors and WEIM Governing Body briefing |
|
Annual policy initiatives roadmap process - 2023 Jun 30, 2022 | Completed | Mar 29, 2023 Final catalog and roadmap posted | May 17, 2023 Briefing to Board of Governors and WEIM Governing Body | |
Annual policy initiatives roadmap process - 2024 Oct 31, 2023 | Active | |||
Budget and grid management charge process - 2022 Jul 12, 2021 | Completed | Dec 20, 2021 Final 2022 Budget and Grid Management Charge Rates Book posted | Dec 15-16, 2021 Board of Governors approval | |
Budget and grid management charge process - 2023 Jul 13, 2022 | Completed | Jan 05, 2023 Final 2022 budget and grid management charge rates book posted | Dec 14, 2022 Board of Governors approval | |
Budget and grid management charge process - 2024 May 03, 2023 | Completed | Dec 14, 2023 Final 2024 budget and grid management charge rates book posted |
Dec 21, 2023 FERC approval (ER23-2974) Dec 14, 2023 Board of Governors approval Sep 29, 2023 Tariff amendment (ER23-2974) |
|
Budget and grid management charge process - 2025 Mar 08, 2024 | Active |
Nov 05, 2024* Meeting Nov 12, 2024* Comments due |
||
Cost of service study - 2023 May 30, 2023 | Completed |
|
Dec 21, 2023 FERC approval (ER23-2974) Sep 29, 2023 Tariff amendment (ER23-2974) Sep 20, 2023 Board of Governors approval |
|
Flexible capacity needs assessment - 2022 Dec 09, 2020 | Completed | Apr 14, 2021 - 2022 final flexible capacity needs assessment posted | ||
Flexible capacity needs assessment - 2023 Dec 15, 2021 | Completed | May 17, 2022 Final assessment posted | ||
Flexible capacity needs assessment - 2024 Dec 15, 2022 | Completed | May 17, 2023 Final assessment posted | ||
Flexible capacity needs assessment - 2025 Dec 13, 2023 | Completed | May 13, 2024 Final assessment posted | ||
Local capacity requirements process - 2022 Oct 27, 2020 | Completed | Apr 30, 2021 Final 2022 and 2026 technical reports | ||
Local capacity requirements process - 2023 Oct 19, 2021 | Completed | Apr 28, 2022 Final 2023 and 2027 technical reports posted | ||
Local capacity requirements process - 2024 Oct 13, 2022 | Completed | May 01, 2023 Final 2024 and 2028 technical reports posted | ||
Local capacity requirements process - 2025 Oct 10, 2023 | Completed |
Apr 04, 2024 Draft final report and technical reports posted May 01, 2024 Final report posted |
||
Local capacity requirements process - 2026 Oct 03, 2024 | Active | Oct 31, 2024* Meeting | ||
Participating transmission owner per unit costs - 2021 Mar 26, 2021 | Completed | Apr 1, 2021 Final per unit cost guides posted | ||
Participating transmission owner per unit costs - 2022 Feb 08, 2022 | Completed | Apr 01, 2022 Final per unit cost guides posted | ||
Participating transmission owner per unit costs - 2023 Feb 13, 2023 | Completed |
Sep 18, 2023 Final cost guides posted |
||
Tariff clarifications filing - 2023 Jun 06, 2023 | Completed | Jul 14, 2023 Final tariff matrix posted |
Oct 24, 2023 FERC approval (ER23-2557) Aug 03, 2023 Tariff amendment filing (ER23-2557) |
|
Tariff clarifications filing process - 2024 Jun 05, 2024 | Active | July 2024 Final tariff language posted |