5.
Please provide your organization's comments on the Economic Study Requests.
California Western Grid makes the following economic study request:
March 14, 2023
regionaltransmission@caiso.com
California Independent System Operator (“CAISO”)
250 Outcropping Way
Folsom, CA 95630
Dear CAISO Transmission Planning,
California Western Grid Development LLC (“California Western Grid”) appreciates the opportunity to comment on the CAISO’s 2023-2024 Draft Study Plan and submit this economic study request for the Pacific Transmission Expansion Project (“PTE” or “PTEP”). We also hereby request that the CAISO studies the PTEP as a solution to the reliability needs described herein and as a transmission solution needed to accommodate deliverability and the State Public Policy needs identified in Senate Bill No. 887 (“SB 887”). Given that the PTEP addresses all of these various needs, we request that the CAISO considers these study requests at the appropriate time in the 2023-2024 Transmission Planning Process (“TPP”). We request that the PTEP is analyzed on the basis of its cumulative reliability, economic, deliverability, and public policy benefits, and that the CAISO avoids analyzing benefits in individual silos. Analyzing all of the benefits of a project is the best approach for “no regrets” planning, in our opinion.
The PTEP, as per our October 14, 2022, filing, is a controllable 2,000 MW HVDC system utilizing subsea cables, which the CAISO has found will allow existing power available at the Diablo Canyon 500 kV switchyard, new sources of offshore wind (“OSW”), or other new sources of renewable energy to be delivered to and between northern and southern California. The CAISO has also determined that the project can reduce Local Capacity Requirements (“LCR”) in the West LA Basin by 1,993 MW, thereby displacing the need to rely on a similar amount of local capacity. The PTEP is described in Section 4.8.2 of the CAISO’s 2021-2022 Board Approved Transmission Plan dated March 17, 2022 (“2021-2022 Report”). California Western Grid requests the PTEP to be re-studied in the 2023-2024 Transmission Planning Process (TPP), with the following HVDC converter stations:
- One 2,000 MW, ±525 kV HVDC bipole converter station located at the northern terminus of the project, connecting either at the Diablo Canyon 500 kV AC station or the future Morro Bay 500 kV AC station.
- One 2,000 MW, ±525 kV HVDC bipole converter station located near the El Segundo 220 kV AC substation, with underground HVDC cables from the shoreline to the converter, and the following AC connections:
- Two 220 kV AC underground cable circuits to El Nido substation; and
- Two 220 kV AC underground cable circuits to La Fresa substation.
California Western Grid also encourages the CAISO to evaluate different configurations of the PTEP, to the extent CAISO Staff thinks appropriate, including multi-terminal configurations and alternative points of interconnection (POI).
In the 2021-2022 Report, the CAISO stated that:
The potential PTE project benefit of reducing capacity requirements needs to be reassessed in future planning cycles as the assumptions change, particularly if the need to retain the existing gas-fired fleet for system-wide resource reliability purposes is relaxed.
Some of the assumptions related to the study of the PTEP have changed, which warrants the reassessment of the PTEP, and we call you attention tothe following five factors:
- Senate Bill No. 887
In 2022, the Legislature unanimously approved and the Governor signed SB 887 into law. SB 887 identifies an urgent State Public Policy need for new transmission that can deliver renewable energy into currently transmission constrained load centers. SB 887 states that considering the CAISO’s FERC approved tariff that requires the CAISO to plan and approve transmission needed to meet state, federal, and local public policy needs, the legislature expects CAISO to take notice of the State Public Policy needs identified in SB 887.
- CAISO 20-Year Transmission Outlook
The CAISO’s first-ever 20-Year Outlook was issued on January 31, 2022. In the Outlook, the CAISO states that:
The CAISO expects to conduct additional stakeholder dialogue through 2022 about next steps as well as the long-term architecture set out in this 20-Year Outlook. Those additional efforts, together with the 20-Year Outlook and evolving resource planning and procurement, will inform the CAISO’s annual transmission planning processes that approve and initiate specific projects.[1]
The 20-Year Outlook anticipates 15,000 MW of gas plant retirements by 2040, including 3 to 5 GW of retirements in the Los Angeles Basin and Big Creek-Ventura area. [2] In the Outlook, the CAISO found a need for an HVDC system from Diablo to LA and stated that the PTEP is an example of the line that is needed.[3]
- California Public Utilities Commission Decision Ordering Supplemental Mid-Term Reliability Procurement (2026-2027) and Transmitting Electric Resource Portfolios to the California Independent System Operator for the 2023-2024 Transmission Planning Process Issued February 23, 2023, in R. 20-05-003
This Decision by the California Public Utilities Commission (“CPUC”) transmits a Base Case Portfolio for the CAISO to use for transmission planning that includes the following:
- “86 GW of new resources by 2035, on top of the existing resource mix on the electric grid of approximately 75 GW. This is more than a doubling of nameplate capacity on the system within 12 years.”[4]
- A 30 million metric ton (“MMT”) target, high transportation electric loads, and 4.7 GW of OSW.
- Even without the 86 GW of additional new generation in the Base Case Portfolio, the CAISO is experiencing deliverability issues associated with interconnecting new generation
The PTEP provides several deliverability benefits to the Bulk Electric System. These include the ability to deliver power directly from Central California to West LA, offset LCR within the LA Basin Local Capacity Area (“LCA”) and provide much needed transmission capacity between northern and southern California. The PTEP had previously demonstrated and was confirmed by the CAISO to reduce local capacity requirements within the LA Basin, potentially allowing for the replacement of up to 1,993 MW of thermal gas fired generation capacity. The PTEP will deliver 2,000 MW into the LA Basin, providing a 1:1 benefit in reducing the need for existing gas-fired generation in the LA Basin. These power injections also provide mitigation for some of the Southern California Edison (“SCE”) metro area contingency overloads identified in the CAISO 2022-2023 Transmission Planning Process (“TPP”).
The PTEP also provides significant benefits in mitigating high flows on Path 26. Path 26 continues to be identified as a congested path and in the 2022-2023 TPP the PTEP was identified as providing high effectiveness in relieving flows under contingency conditions.
- The CAISO has found that the PTEP provides valuable transfer capacity that can reduce reliance on the LA Area gas plants and the Aliso Canyon Gas Storage Facility
At the November 17, 2022, stakeholder presentation, the CAISO provided the results of a sensitivity study showing that the PTEP could reduce dependence on the Aliso Canyon Gas Storage Facility and allow, but not require, it to retire. This is an important benefit considering the State’s desire to close that facility at some point in the near term.
In light of the preceding factors affecting the assumptions made in previous studies of the PTEP, we request the CAISO to study the PTEP as a transmission solution that will provide multiple benefits to CAISO ratepayers, including mitigation of Path 26 congestion, reduced renewable curtailment, and substantial Local Capacity Benefits.
In California Western Grid’s October 14, 2022, filing for the 2022-2023 TPP[5], we submitted an independent analysis performed by E3 of the benefits the PTEP will provide, even if the gas plants remain in service through the study period. California Western Grid hereby incorporates the October 14 filing herein by reference and will not repeat the many benefits analyzed therein. The E3 analysis concludes that, without retirement of any gas generation and without quantifying many of the known benefits of the PTEP (wildfire risk reduction, reduced reliance on Aliso Canyon, air quality improvement especially among underserved communities, etc.), economic benefits of the PTEP would offset 50% or more of the PTEP’s cost. The benefits not quantified include environmental air quality benefits that lie at the core of the State’s energy goals, as well as wildfire mitigation benefits that SB 887 requires to be considered in planning new transmission. This raises an important planning issue. We urge the CAISO not to evaluate the benefits of the PTEP in separate silos, but rather in terms of the cumulative benefits the PTEP provides, including the benefit of accommodating the need for transmission for State Public Policy needs identified in SB 887. There are many other non-quantifiable public policy benefits that the PTEP addresses and a silo approach to analyzing benefits is sure to ignore the true value of a project like the PTEP.[6] In terms of the quantifying the benefits of the PTEP, we request that the CAISO utilize the E3 methodology, which anticipates storage (not gas-fired generation) will be the marginal Resource Adequacy (“RA”) resources in the 2030’s and beyond. The E3 methodology is described in detail in the October 14th filing.
We disagree with the CAISO’s historic approach to continue using conservative valuations for LCR benefits as mentioned above. We believe the E3 methodology is a superior approach to calculating LCR benefits and should be used by the CAISO to quantify LCR reduction benefits.
But even if the CAISO continues to use gas plants as the marginal RA resource in the 2030’s and beyond, the CAISO valuation understates the actual cost of LCR when procured from existing gas fired resources . Based on the publicly available FERC EQR data for 2021, the weighted average price of local capacity contracts in the Western LA Basin ranges between $4.86/kW-month and $7.45/kW-month. This is based on an analysis of the publicly available FERC EQR data for existing RA contracts totaling 2,434 MW of existing gas plants in the LA Basin. This is in sharp contrast to the approximately $2.00 / kw/mo. the CAISO has historically use as the cost of LCR procurement in the LA Basin.
.
If the CAISO had valued the LCR benefits for the PTEP at the current 2021 LA Basin capacity costs, the LCR benefit for the PTEP would have ranged from $1,604 million to $2,459 million net present value and resulted in a benefit-to-cost ratio between 0.76 and 1.11. A result that should have qualified a project for approval in the 2021-22 TPP when combined with all of the additional reliability, deliverability, and Public Policy benefits.
California Western Grid submits that the CAISO TPP will not achieve its objective of providing helpful information to State policy makers and regulatory agencies by continuing to use “conservatively” low or outdated values for local capacity.
We agree with and support the CAISO’s previous comment to the Commission that transmission solutions can have long lead times and, therefore “planning for transmission-dependent projects should start as soon as possible.”[7] Indeed, if the State is to reach its 2030, 2035, and 2045 greenhouse gas (“GHG”) SB 100 requirements in a reliable and least-cost manner, the CAISO must begin planning now for transmission solutions that reduce LCRs that currently cause reliance on local fossil fuel-fired resources. To do so, the CAISO will need to change its conservative assumptions and use realistic capacity values in its economic analysis and should begin to incorporate the added cost of operating and maintaining the generation plants that are providing LCR capacity.
We appreciate the CAISO’s consideration of these comments, and we urge the CAISO to re-study the PTEP in the 2023-24 TPP consistent with the comments herein. We are available to discuss the PTEP’s many benefits with CAISO transmission planners at your convenience.
Thank you for your consideration.
Sincerely,
Marty Walicki
Martin Walicki
on behalf of California Western Grid Development, LLC
[1] 20-Year Outlook, page 57.
[2] 20-Year Outlook, Table 3.1-4: Assumed gas-fired generation retired by local capacity area.
[3] 20-Year Outlook, pages 48-49.
[4] CPUC Decision 23-02-040, page 47.
[5] (“October 14th Filing.)” See, pp 30-32 of Attachment A.
[6] See also, October 14th Filing at 32.
[7] See CAISO comments filed on March 12, 2020, with respect to the Administrative Law Judge’s Proposed Decision on the “2019-2020 Electric Resource Portfolios to Inform Integrated Resource Plans and Transmission Planning”.