1.
Please provide your organization’s feedback on the November 1, 2023 Resource Modeling and Program Design Working Group Meeting.
Problem Statement 1: There is a need for additional consistent, transparent, and timely information on the sufficiency of the RA fleet in the CAISO Balancing Authority Area (BAA). Without this, there are challenges in:
• Accessing and communicating the system wide sufficiency of the CAISO BAA in light of the contracted RA fleet; and
• Addressing such concerns in a timely and efficient manner.
Sub-issues:
• An RA Portfolio Evaluation does not exist today
• There is a lack of Non-RA Visibility
• The default Planning Reserve Margin is outdated
Western Area Power Administration Sierra Nevada Region (WAPA SNR) appreciates the opportunity to provide input to the Resource Adequacy modeling and program design. As a federal agency, WAPA SNR is responsible for marketing federal hydropower generated by the Central Valley Project (CVP) to meet its statutory responsibilities to serve project-use energy pumping requirements and market available hydropower generation under its Power Marketing Plan to preference power allottees. In northern California, WAPA SNR serves load in both the Balancing Authority of Northern California and the CAISO. WAPA SNR delivers its generation from many large and small hydro facilities of the CVP to its loads. WAPA SNR owns, operates, and maintains an extensive high voltage transmission network extending to the load center of Northern California. To a large extent, WAPA SNR’s generation, supplemented by power purchases from the Pacific Northwest, supported by its transmission network, follows its load in the CAISO, especially in the spring and summer.
As a Local Regulatory Authority (LRA), WAPA SNR established its own Resource Adequacy (RA) Plan and published it in the Federal Register/Vol. 72, No. 144/Friday, July 27, 2007/Notices. In the RA plan, WAPA designates its hydroelectric facilities in the Balancing Area of Northern California (BANC) as a system resource with 100 percent of its forecasted capacity as Qualifying Capacity, which is determined by the 50 percent rolling 12-month forecast for the appropriate month. Due to Federal policies in support of the Marketing Plan in WAPA SNR’s marketing and operations processes, WAPA SNR cannot make CVP hydroelectric units available to the CAISO for Planning Reserve Margin (PRM). WAPA uses the CVP hydroelectric units as Qualifying Capacity to meet WAPA SNR’s load in the CAISO Balancing Authority Area. WAPA currently does not own or operate any conventional thermal or intermittent generation resources. WAPA has been using capacity procured from qualifying resources to meet its PRM obligations.
In recent years, WAPA SNR has experienced increased difficulty in procuring RA capacity from the market and the price for RA capacity has increased drastically. WAPA SNR believes this is the core problem to be addressed by this RA modeling and program design initiative. The high price is caused by shortage of supply due to the decrease of conventional generation, the unrecognized RA capacity due to CAISO counting rules or CIRA system limitations, and the inflated demand for RA capacity due to misapplication of operational criteria to planning capacity. WAPA SNR believes the important and the urgent issue is how to address the broken RA market. When load serving entities have problem procuring RA capacity even at ever increasing prices, the solution is not to increase the RA demand that is already inflated. The starting point should be to take a closer look at what the CAISO really needs from an operational perspective. For example, does the CAISO really need local RA capacity at a level sufficient to cover the August peak load for all the other months of the year? When the generation fleet was comprised of primarily conventional thermal generators, by ignoring fuel storage and emission limitations, one could perhaps assume that if a generator was supposed to be available in August, it should also be available in April. However, today’s generation mix has changed and therefore the existing rules regarding local RA and must offer obligations are obsolete. WAPA SNR appreciates this timely RA discussion and hope this initiative can focus on the important and urgent challenge of RA capacity shortage for the CAISO and for the load serving entities.
According to the fundamental concept of supply and demand in microeconomics, increasing the demand for the RA capacity by the CAISO will not reduce RA capacity shortage; it will only exacerbate the shortage in the bilateral market and drive up the price even further. Higher market prices for RA at this point does not incentivize more supply for RA capacity because the RA prices are already very high and many RFOs (Requests for Offer) of RA do not receive offers. This phenomenon indicates that the supply curve and the demand curve have no intersection! The RA capacity shortage can only be addressed by the LRAs because RA capacity takes years of planning to install. The generation resource planning process is complicated and influenced by factors beyond short term market prices. Government policy and regulations play a crucial role in the generation resource planning process. Moreover, the generation resource planning process must also balance sufficiency (or abundancy) against costs. The generation planning activities should be left to the LRAs who have jurisdiction over such activities. Each LRA is different because they are subject to different regulations and have different resource mix. They face different challenges that require different solutions. The CAISO has neither the jurisdictional authority nor the LRA-specific domain knowledge or the financial accountability to devise suitable RA plans for all the LRAs. One-size-fit-all solutions will not work.
The CAISO only needs operational capacity regardless of whether it is labeled as RA according to some rules that can be imperfect. For example, the CVP generation provides substantial amount of power and energy to serve California load. But the CVP generation capacity is not recognized by the CAISO as RA capacity because it is a use limited resource outside of CAISO BAA. Since the CVP generators are in BANC, SNR meets its RA obligations for the loads in the CAISO partially using the imports backed-up by the CVP generations. Since imports are not recognized by the CAISO as use limited resources, WAPA is not able to show and get full credit for providing RA using CVP generation. Although physically the CVP generation is providing power and energy to serve load in the CAISO BAA, on the CAISO’s book, the CAISO does not see this capacity as “RA capacity” and cannot use this capacity to reduce its net demand for RA capacity. From power system operation viewpoint, the CAISO just needs working capacity regardless of whether it is labeled as RA or not. WAPA SNR believes that by recognizing all the capacity and by determining sensible capacity requirement, the “RA capacity” shortage situation can be mitigated.
As the CAISO plans to use the extended day-ahead market (EDAM) to enhance reliability and renewal resource integration, WAPA SNR believes that EDAM can also foster RA capacity diversity benefit. For example, the CVP generators would be modeled in the EDAM as generators instead of imports to the CAISO. It makes sense to enable CVP generations to provide RA directly as use limited resources if WAPA SNR joins EDAM. However, the linkage between Resource Sufficiency and Resource Adequacy must be externalized from the EDAM itself because the LRAs are in the best position to ensure their planning capacity is provided to the CAISO in accordance with their RA plan. The CAISO’s focus should be enforcing Resource Sufficiency at the LRA level or the LSE (load serving entity) level through market incentives and settlement consequences. The current EDAM design of enforcing Resource Sufficiency at BAA level is inadequate. The goal should be having every LRA or LSE bring sufficient energy supply to meet their load forecast and sufficient flexible capacity to provide ancillary services and enable congestion management. The onus should be on the LRAs who have the jurisdictional authority over planning to demonstrate their responsibility and accept accountability.
In summary WAPA SNR suggests:
- The primary problem is RA capacity shortage and high prices,
- The CAISO refine its “RA” capacity requirements according to the month of the year and time of the day,
- The CAISO recognize all operationally available capacity to meet its operational needs, and
- The CAISO focus on operational capacity through Resource Sufficiency and leave RA capacity planning responsibilities to LRAs,
- The CAISO leverage “RA” capacity diversity in the EDAM by letting the LRAs and LSEs do their job and accept accountability.
2.
In light of the working group discussion on Problem Statement 1 on visibility and transparency of the reliability of the ISO BAA, please provide any suggested edits to the problem statement. Alternatively, please provide your own problem statement.
In light of the discussion provided above, WAPA suggests the following problem statement.
Problem Statement 1: The primary problem is RA capacity shortage and high RA prices. To reduce net RA capacity demand and increase effective RA capacity supply in the operational timeframe, several sub (or means) problems can be addressed by CAISO market design without encroaching LRA’s jurisdictional authority:
- Refine the CAISO’s local RA requirements according to the month of the year and the time of the day, instead of applying August peak load to all other months of the year.
- Consider all available capacity in assessing operational needs and backstop procurement in the operational time frame regardless of whether such capacity is labeled as RA or not according to rules of the LRAs.
- Hold LRAs responsible for bringing sufficient operational capacity to the CAISO (EDAM) by validating and settling the shortage penalties associated with Resource Sufficiency at LRA or LSE level.
- Recognize use limited (e.g., energy limited) resource in the EDAM footprint in assessing RA capacity and operational capacity eligibility and requirements.
- Enhance or overhaul the CAISO’s CIRA system to allow all LRAs to show RA capacity to the CAISO according to the LRA’s RA plans to improve transparency and CAISO’s visibility.