INITIATIVE:
Aliso Canyon gas-electric coordination

Started: Mar 23, 2016

Leads
Brittany Dean

Phase 1 of this initiative addressed the gas-electric market coordination concerns raised by the limited operations of the Aliso Canyon gas storage facility. The resulting provisions were approved by FERC and will sunset on Nov. 30, 2016. Aliso Canyon Phase 2 will evaluate and propose to either retire, extend or adjust the interim measures approved for the summer period and will file with FERC to seek authority to retain the needed measures through the winter period. Phase 3 proposes to extend the temporary market and operational tools currently in place so that they remain in effect beyond Nov. 30, 2017. Phase 4 proposes to further extend the measures for an additional year. Phase 5 proposes to permanently retain the maximum gas burn constraint in the Southern California region.

Status

Proposal Development Decision Implementation Completed/Closed
Phase 5
Oct 07, 2019 Draft tariff language posted
Dec 31, 2019 FERC approval (ER20-273)
Oct 31, 2019 Tariff amendment filing (ER20-273)
May 20, 2021 Deployment
May 20, 2021 Activation
Completed
Phase 4
Sep 17, 2018 Draft tariff language posted
Feb. 8, 2019 FERC approval
Sept. 28, 2018 Tariff amendment filing (ER18-2520)
Dec 16, 2018 Effective
Nov 30, 2018 Effective
Completed
Phase 3
Jun 22, 2017 Draft final proposal posted
Dec 15, 2017 FERC approval (ER18-375)
Nov 28, 2017 FERC approval (ER17-2568)
Dec 1, 2017 Tariff amendment filing (ER18-375)
Sep 29, 2017 Tariff amendment filing (ER17-2568)
Jul 26, 2017 Board of Governors approval
Dec 16, 2017 Effective
Nov 30, 2017 Effective
Completed
Phase 2
Sep 23, 2016 Draft final proposal posted
Nov 28, 2016 and Mar 24, 2017 FERC approval
Oct 14, 2016 Tariff amendment filing (ER17-110)
Oct 3, 2016 Board of Governors approval
Nov 30, 2016 Effective
Completed
Phase 1
May 05, 2016 Revised draft final proposal posted
Aug. 26, 2016 FERC approval
May 09, 2016 Tariff amendment filing (ER16-1649)
May 04, 2016 Board of Governors approval
Jul 06, 2016 Activation
Jun 02, 2016 Activation
Completed

Phase 5

Completed

Phase 5 of this initiative included enhancements to the existing dynamic competitive path assessment methodology employed currently in the locational market power mitigation mechanism in the day-ahead market and the real-time market.

It also included enhancements to the gas nomogram functionality to eliminate non-optimal gas burn limitation scenarios and provide flexibility for operation engineers and operators to fully assess operational conditions.




Web meeting


Draft Tariff Language - Aliso Canyon Gas-Electric Coordination Phase 5

Presentation - Aliso Canyon Gas-Electric Coordination Phase 5 - Draft Tariff Language - Oct 7, 2019

Phase 4

Completed

Outcome: Effective Nov 30 and Dec 16, 2018, Phase 4 extended certain interim temporary market and operations provisions to remain in effect until Dec 31, 2019.

Web meeting


Draft Tariff Language - Aliso Canyon Gas-Electric Coordination Phase 4

Phase 3

Completed

Outcome: Effective Nov 30 and Dec 16, 2017, Phase 3 extended the interim temporary market and operational provisions to remain in effect until Nov 30, 2017.


Notice of Initial Decisional Classification - Aliso Canyon Gas Electric Coordination Phase 3

Web meeting


Revised Draft Tariff Language - Aliso Canyon Gas-Electric Coordination Phase 3

Draft Tariff Language - Aliso Canyon Gas-Electric Coordination Phase 3

Web meeting


Draft Final Proposal - Aliso Canyon Gas-Electric Coordination Phase 3

Agenda and Presentation - Aliso Canyon Gas-Electric Coordination Phase 3 Draft Final Proposal

Web meeting


Straw Proposal - Aliso Canyon Gas-Electric Coordination Phase 3

Agenda and Presentation - Aliso Canyon Gas-Electric Coordination Phase 3

Phase 2

Completed

Outcome: Phase 2 extended the interim measures approved for the summer period and retained those provisions through the winter period, as approved by FERC.

Web meeting


Draft Tariff Language - Aliso Canyon Gas-Electric Coordination Phase 2

Web meeting


Draft Final Proposal - Aliso Canyon Gas-Electric Coordination Phase 2

Agenda and Presentation - Aliso Canyon Gas-Electric Coordination Phase 2 - Draft Final Proposal

Web meeting


Agenda and Presentation - Aliso Canyon Gas-Electric Coordination Phase 2 - Straw Proposal

Phase 1

Completed

Outcome: The ISO activated on Jun 2, 2016, two features: 1) the ability to rebid commitment costs for resources not picked up in the day ahead market, and 2) a new CMRI report showing the D+2 report was populated on Jun 5, 2016. On Jul 6, the ISO activated adjusted gas price indexes to calculate commitment and default energy bids for affected resources in the Southern California Gas Company and San Diego Gas & Electric systems, and gas price information used to increase efficiency of economic dispatch.


Joint agency collaboration action plan and technical reports for local energy reliability in summer 2016

Web meeting


Draft Tariff Language - Aliso Canyon Gas-Electric Coordination

Web meeting


Revised Draft Final Proposal - Aliso Canyon Gas-Electric Coordination
Updated stakeholder schedule

Draft Final Proposal - Aliso Canyon Gas-Electric Coordination

Agenda and Presentation - Aliso Canyon Gas-Electric Coordination

In-person meeting


Market Surveillance Committee meeting

Straw Proposal - Aliso Canyon Gas-Electric Coordination

Aliso Canyon Gas Electric Coordination Discussion - ISO Presentation - Apr 2016

In-person meeting


Aliso Canyon Gas Electric Coordination Alternative Template

Aliso Canyon Gas Electric Coordination - Gas Electric Coordination Process

Agenda and Presentation - Aliso Canyon Gas Electric Coordination - Working Group

In-person meeting


Issue Paper - Aliso Canyon Gas-Electric Coordination

Agenda and Presentation - Aliso Canyon Gas Electric Coordination