Local capacity requirements process - 2027

Started: Sep 16, 2025

Leads
Catalin Micsa

The ISO performs annual studies to identify the minimum local resource capacity required in each local area to meet established reliability criteria. As part of this study process, the ISO obtains input from stakeholders on the criteria, methodology and assumptions used as inputs into the studies, and feedback on the study results. Based on the study results, load serving entities receive a proportional allocation of the minimum required local resource capacity by transmission access charge area, and submit resource adequacy plans to show that they have procured the necessary capacity.

Status

Development Decision Implementation Completed/Closed
Nov 03, 2025 Meeting
Nov 17, 2025 Comments due
Feb 24, 2026* Draft study posting
Mar 2, 2026* Draft study results posting
Mar 9, 2026* Meeting
Mar 23, 2026* Comments due
Apr 2, 2026* Draft final report posting
Apr 1, 2026* Draft final report posting
Apr 9, 2026* Meeting
Apr 16, 2026* Comments due
Apr 30, 2026* Final report posting

Activities

Study manual


Presentation - 2027 Local Capacity Technical Study Criteria Methodology and Assumptions - Nov 03, 2025

Draft Study Manual - 2027 Local Capacity Requirements

Submit comments Due: Nov 17, 05:00 pm