INITIATIVE:
Western EIM sub-entity scheduling coordinator role

Started: Nov 03, 2020

Leads
Danny Johnson

The objective of this initiative is to create a new EIM sub-entity scheduling role that allows for multiple scheduling coordinators within a single EIM entity balancing authority area to schedule and settle non-participating loads and resources.

Status

Proposal Development Decision Implementation Completed/Closed
Jan 21, 2021 Revised straw proposal
Jan 28, 2021 Meeting
Feb 18, 2021 Comments due
May 06, 2021 EIM Governing Body meeting
May 19-20, 2021 Board of Governors meeting

Activities

Web meeting


Revised Straw Proposal - Western EIM Sub-Entity Scheduling Coordinator Role

Web meeting


Presentation - EIM Sub-Entity Scheduling Coordinator Role - Nov 12, 2020

Issue Paper/Straw Proposal - Western EIM Sub-Entity Scheduling Coordinator Role

View comments