The primary objective of Interconnection Process Enhancement (IPE) 5.0 is to address commitments the ISO made during IPE 2023, where the ISO made foundational changes to its interconnection procedures, which were approved by FERC. The designation "5.0" reflects that this is the fifth iteration of the IPE initiative.
Proposal Development | Decision | Implementation | Completed/Closed |
---|---|---|---|
Aug 04, 2025* Straw proposal posting
Aug 11, 2025* Meeting Aug 25, 2025* Comments due Oct 13, 2025* Draft final proposal posting Oct 20, 2025* Meeting Nov 03, 2025* Comments due |
Scoping document |
Scoping Document - Interconnection Process Enhancements 5.0 - Jul 08, 2025 07/08/2025
|
View comments |