This initiative will address the California ISO’s compliance with FERC Order No. 881 in establishing new transmission line rating requirements
Proposal Development | Decision | Implementation | Completed/Closed | |
---|---|---|---|---|
Phase 2 |
Jun 16, 2023 Compliance Filing (ER22-2362)
|
Nov 21, 2024 Comment deadline
Implementation milestones
Apr 01, 2024 - track 1 Q4 2024 - track 2 |
||
Phase 1 |
Jun 23, 2022 Revised draft tariff language posted
|
Apr 20, 2023 FERC approval (ER22-2362)
Jul 12, 2022 Compliance filing (ER22-2362) |
Dec 16, 2024 Stakeholder call
Implementation milestones
Dec 12, 2024 Comments due Dec 05, 2024 Revised draft tariff language posted |
Through Phase 2 of this initiative, the ISO will coordinate with participating transmission owners, WEIM entities, market participants, and RC West customers to address implementation issues and milestones associated with new transmission line rating requirements under Order No. 881.
This initiative will address the California ISO’s compliance with FERC Order No. 881 in establishing new transmission line rating requirements