The 2023 Interconnection Process Enhancements (IPE) initiative is focused on enhancing coordination of resource procurement and interconnection, resource planning and transmission planning to achieve state reliability and policy needs. In the 2023 IPE initiative the CAISO intends to consider more fundamental changes to the Generator Interconnection and Deliverability Allocation Procedures than were considered in IPE 2021.
Proposal Development | Decision | Implementation | Completed/Closed | |
---|---|---|---|---|
Phase 2 | ||||
Phase 1 |
Track 2
Oct 17, 2024 FERC filing Track 3 Jan 09, 2025 Draft final proposal posted Feb 19, 2025 Final proposal posted Mar 27, 2025 Draft tariff language posting Mar 29, 2025* Board of Governors meeting Apr 07, 2025 Comments due Apr 09, 2025 Meeting |
Track 2
Jun 12, 2024 Board of Governors approval Track 1 Aug 01, 2023 FERC approval (ER23-2058) Jun 02, 2023 Tariff amendment filing (ER23-2058) May 17, 2023 Board of Governors approval |