2026-2027 Transmission planning process

Started: Jan 07, 2026

Leads
Jeff Billington

The California ISO 2026-2027 transmission planning cycle involves key stakeholder activities from 2026 through early 2027. Each year, the ISO conducts its transmission planning process to identify potential system limitations as well as opportunities for system reinforcements that improve reliability and efficiency. The transmission planning process core product is the ISO Transmission Plan, which provides an evaluation of the ISO control grid, examines conventional grid reliability requirements and projects, summarizes key collaborative activities and provides details on key study areas and associated findings.

Status

Development Decision Implementation Completed/Closed
Dec 30, 2025 30-day Comment period begin - study plan development
Feb 19, 2026* Draft study plan posting
Feb 24, 2026* Meeting
Mar 10, 2026* Comments due
Mar 31, 2026* Final study plan posting
Aug 14, 2026* Post preliminary reliability study results and mitigation solutions
Aug 28, 2026* Post scenario base cases
Sep 23, 2026* Meeting (day 1)
Sep 24, 2026* Meeting (day 2)
Oct 08, 2026* Comments due
Oct 30, 2026* Post final reliability study results
Nov 16, 2026* Post preliminary assessment of policy and economic planning studies
Nov 18, 2026* Meeting
Dec 04, 2026* Comments due
Mar 31, 2027* Draft transmission plan posting
April 7, 2027* Meeting
May, 2027* Board of Governors
May 31, 2027* Final board-approved transmission plan posting

Activities


Stakeholder comment period for 2026-2027 unified planning assumptions and study plan is Dec 30, 2025 through Jan 30, 2026. See the notice for more information.

Letter - Data Request and Invitation to 2026-2027 Transmission Planning Process - Dec 30, 2025